Process support for the conversion to SAP-LVS at plant Luhe Wildenau
Siemens Mobility GmbH, 91052 Erlangen
manufacture of control cabinets and electronic components
Project execution
2016
Our performance:
– support in the implementation of integration SAP-LVS As a complete storage concept with automatic storage space allocation and following picking
– analysis IS-processes
– definition of TARGET-processes and layouts
– planning organization for „go live“
– monitoring and implementation in teamwork
– training processes => „5-S-philosophy“
– stabilization processes to „go live“
– documentation and visualization TARGET-processes
Particularities:
– no stocks available at stock level => error, inefficiency
– high stock level
– „go live“ during production with storage conversion
– several types of bearings (KANBAN-warehouse+ cable bearing)
Achieved goals:
– functional modular bearing direct to „go live“
– 30-40% Increased efficiency
– clear / Simple processes Rethinking logistical workers
– correct stock levels